33
15/02/2011 - 300014279-001-J DTG(E)130 - 35/45/65/90/115 Eco.NOxPlus
8. Connecting the furnace
8.4.1 Classification
(x) For Germany only
Belgium: Boilers can only be installed with flue gas connection pipes
provided by the constructor. For the list of parts, refer to the current
price list.
6
C001246
1
2
2
7 333 4 25
1
Homologation C
13x
: Air/flue gas connection by means of concentric
pipes to a horizontal terminal (so-called forced flue)
2
Homologation C
33x
: Air/flue gas connection by means of concentric
pipes to a vertical terminal (roof outlet)
3
Homologation C
93x
: Air/flue gas connection by concentric pipes in
the boiler room and single pipes in the chimney (combustive air in
counter current in the chimney)
4
Homologation C
93x
: Air/flue gas connection by concentric pipes in
the boiler room and single "flex" in the chimney (combustive air in
counter current in the chimney)
- Only factory components are authorised for connecting
the boiler and the terminal.
- The clear section must comply with the standard.
- The chimney must be swept before the installation of the
evacuation conduit.
5
Homologation C
53
: Air and flue gas connection separated by means
of a bi-flow adapter and single pipes (combustive air taken from
outside)
6
Homologation B
23P
: Chimney connection (combustive air taken
from the boiler room)
7
Homologation B
23P
: Cascade installation
Compulsory accessories:
Flue damper (Package HC154)
Alarm and control module AM35 (Package GR12)
For information about the connection to the electrical terminal block,
refer to the instructions delivered with package GR12